Under an NEC Target Cost contract, British Gas was contracted to design and deliver energy saving measures to Guy’s and St Thomas’ Hospitals, which were guaranteed to produce energy savings of £1.2 million per year, guaranteed and underwritten for a 10-year period.
The design and management elements of the contract, worth £2.5 million, were fixed costs but the construction direct costs of £6.6 million were reimbursable, with a clause under which the contractor benefitted if the savings were delivered at a lower actual cost.
The contract lasted from December 2015 to January 2019 and savings of £1.3 million per year were achieved with the contractor managing to achieve a significant underspend of the reimbursable costs.
The energy savings were achieved through a variety of measures including:
Ridge provided commercial support in the following areas: